Project Performance Analysis in Hydrant and Plumbing. Case Study: Biopharmaceutical Manufacturing Facility

Karya Sejuk Mandiri is a general contractor company primarily engaged in Mechanical, Electrical, and Plumbing (MEP) which is currently working on Plumbing and Hydrant work with a work value of Rp586,000,000 with an estimated completion time of 7 months.

From the budget aspect data, this project is projected to experience a cost overrun of Rp82,099,035 and an additional 23 weeks of working time. This condition can get worse if PT. Karya Sejuk Mandiri did not take corrective action for the losses incurred.

The study begins by analyzing the level of work performance as an initial reference that the job is in trouble. Using the Current Reality Tree (CRT), this study finds two root causes of problems that cause work to experience cost overruns and delays. Three alternative options are given for each root cause of the problem and then selected using the Analytical Hierarchy Process (AHP) to get the best course of action.

This research concludes by providing two corrective actions and also a plan for their implementation during the work. Thus, it is hoped that there will be an increase in the level of performance so that the project can be completed properly.