Abstract :
Karya Sejuk Mandiri is a general contractor company primarily engaged in Mechanical, Electrical, and Plumbing (MEP) which is currently working on Plumbing and Hydrant work with a work value of Rp586,000,000 with an estimated completion time of 7 months.
From the budget aspect data, this project is projected to experience a cost overrun of Rp82,099,035 and an additional 23 weeks of working time. This condition can get worse if PT. Karya Sejuk Mandiri did not take corrective action for the losses incurred.
The study begins by analyzing the level of work performance as an initial reference that the job is in trouble. Using the Current Reality Tree (CRT), this study finds two root causes of problems that cause work to experience cost overruns and delays. Three alternative options are given for each root cause of the problem and then selected using the Analytical Hierarchy Process (AHP) to get the best course of action.
This research concludes by providing two corrective actions and also a plan for their implementation during the work. Thus, it is hoped that there will be an increase in the level of performance so that the project can be completed properly.
Keywords :
analytical hierarchy process, Cost Overruns, Current Reality Tree, Project Delays, Work Performance.References :
- Merriam-Webster. (n.d.). Lump sum. In Merriam-Webster.com dictionary. Retrieved August 25, 2022, from https://www.merriam-webster.com/dictionary/lump%20sum
- Shashikant Gopal Kamble, & Prof. M. B. Kumthekar. (2015). Problems Associated With Plumbing and its Maintenance. International Journal of Engineering Research And, V4(04). https://doi.org/10.17577/ijertv4is040484
- Collins Dictionary. (n.d.). Fire hydrant. In Collins dictionary. Retrieved August 25, 2022, from
https://www.collinsdictionary.com/dictionary/english/fire-hydrant#:~:text=countable%20noun,for%20putting%20out%20a%20fire
- Willmer Limited. (2014, October). White Paper – Using S-Curves to improve Project Performance. https://projectpro-ph.com/wp-content/uploads/2017/03/Using-S-Curves-to-Improve-Project-Performance.pdf
- , Wadugodapitiya, & Sandanayake, Y. & Thurairajah, Niraj. (2010). Building Project Performance Evaluation Model. https://www.researchgate.net/publication/332846660_Building_Project_Performance_Evaluation_Model
- Eirgash, M. A. (2021). Project Monitoring and Early Warning of Time-Cost Overruns in Earned Value Management. Current Trends in Civil & Structural Engineering, 7(5). https://doi.org/10.33552/ctcse.2021.07.000673
- Kim, Byung-Cheol. (2007). Forecasting Project Progress and Early Warning of Project Overruns with Probabilistic Methods. https://www.researchgate.net/publication/41014773_Forecasting_Project_Progress_and_Early_Warning_of_Project_Overruns_with_Probabilistic_Methods
- Kumbhar, Kalayan. (2018). Brainstorming technique: Innovative Quality Management Tool for Library. https://www.researchgate.net/publication/325594636_Brainstorming_technique_Innovative_Quality_Management_Tool_for_Library
- Alutbi, Mohaymen. (2020). WORK BREAKDOWN STRUCTURE (WBS).
https://www.researchgate.net/publication/342163727_WORK_BREAKDOWN_STRUCTURE_WBS
- Brief, ©.M. (n.d.). What is a Current Reality Tree? Definition and meaning. MBA Brief. Retrieved August 26, 2022, from https://www.mbabrief.com/what_is_current_reality_tree.asp
- JD Edwards World. (2007, January). Work Order Management Guide Version A9.1. https://docs.oracle.com/cd/E22655_01/nav/JD_Edwards_World_Work_Order_Management_A91_Guide.pdf
- Project Planning and Management (PPM) V2.0. (2014, August). WBS Dictionary: Software as Service (SaaS) Version 1.0. https://www.hud.gov/sites/documents/WBS_SAAS_DICTIONARY.PDF
- Xuan, Q. L. H., Moslehpour, M., & Tien, D. T. (2019). An evaluation of project management tools and techniques in Vietnam. Management Science Letters, 283–300. https://doi.org/10.5267/j.msl.2018.11.011
- Dokras, U. (2019). The Role of Human Resources in a Project Management Plan.pdf. Indo Swedisg Author’s Collective. https://www.academia.edu/38376823/The_Role_of_Human_Resources_in_a_Project_Management_Plan_pdf?source=swp_share
- Agus, R. (2022, June 28). Banten MENATAP Masa Depan Dari Kawasan Industri – bisnis Indonesia. Bisnisindonesia.id. Retrieved July 4, 2022, from https://bisnisindonesia.id/article/banten-menatap-masa-depan-dari-kawasan-industri
- Fredendall, Lawrence & Patterson, J. & Lenhartz, C & Mitchell, Bryant. (2002). What Should Be Changed? A comparison of cause and effect diagrams and current reality trees shows which will bring optimum results when making improvements. Quality Progress. 35. 50-59.
- Government of Indonesia. Indonesia Investment Coordinating Board. 2019. A Brief Guide of Investment in The Industrial Estates. Jakarta.
- Government of Indonesia. President of the Republic of Indonesia. 2015. Regulation no. 142 of 2015 on Industrial Estate. Ministry of Law and Human Rights of Republic of Indonesia. Jakarta.
- Hanipa, Hepy (2021). Project Cost Overrun Analysis Case Study: A Rotating Equipment Services Company (PT Z).
- Hidayat, F. (2022). ModernCikande Raih Predikat Best Industrial Estate Development. beritasatu.com. Retrieved 4 July 2022, from https://www.beritasatu.com/ekonomi/576070/moderncikande-raih-predikat-best-industrial-estate-development
- Indonesia Window. (2020, October 13). Indonesia’s industrial estate areas increase in five years. Indonesia Window. Retrieved July 4, 2022, from https://indonesiawindow.com/en/indonesias-industrial-estate-areas-increase-in-five-years
- Kawasan Industri ModernCikande Industrial Estate (MCIE) oleh Modern Group. Modern-cikande.co.id. (2022). Retrieved 4 July 2022, from https://www.modern-cikande.co.id/lang_id/aboutus.html.
- (2021, September 20). Kawasan Industri berikan kontribusi signifikan Bagi Ekonomi Daerah. pressrelease.id. Retrieved July 4, 2022, from https://pressrelease.kontan.co.id/release/kawasan-industri-berikan-kontribusi-signifikan-bagi-ekonomi-daerah
- Mahardika, T. (2020, November 24). Gelontorkan RP500 M, jbio Bangun Pabrik biofarmasi Dan Vaksin modern Di Banten. SINDOnews.com. Retrieved July 4, 2022, from https://ekbis.sindonews.com/read/243958/34/gelontorkan-rp500-m-jbio-bangun-pabrik-biofarmasi-dan-vaksin-modern-di-banten-1606212678
- Noviansyah, Angga (2021). Minimizing Project Completion Delays and Operational Cost, A Case Study: Pt. Bina Karya (Persero) Project.
- Project Management Institute. (2017). A guide to the Project Management Body of Knowledge (PMBOK guide) (6th ed.). Project Management Institute.
- Puspaningtyas, L. (2022). Kawasan Industri Halal akan Dapat Insentif Fiskal dan Non-Fiskal |Republika Online. Republika Online. Retrieved 4 July 2022, from https://www.republika.co.id/berita/re8lrd383/kawasan-industri-halal-akan-dapat-insentif-fiskal-dan-nonfiskal
- Sirias, Danilo (1997). Using Theory of Constraints To Teach Introduction to MIS. Proceedings of the International Academy for Information Management Annual Conference.