Abstract :
The research aims to improve AMA Group’s project management to address project delays and identify the root causes. It uses PMBOK as a problem-solving approach, utilizing expert judgment and historical data to identify root causes and assess project management aspects. The root cause of project delays is related to project scope, schedule, and resource management. Work Breakdown Structure (WBS) and Critical Path Method (CPM) are recommended tools for project scope management, scheduling, and resource management. These techniques enable effective change control, comprehensive scope planning, realistic schedule planning, streamlining workflow processes, addressing labour shortages, and regularly reviewing and improving project structures and processes. By integrating these tools, AMA Group can mitigate potential delays and enhance project efficiency.
Keywords :
CPM, PMBOK, Project Delay, Project Resource Management, Project Schedule Management, Project Scope Management, WBSReferences :
- Ahlin, E. M. (2019). Semi-Structured Interviews With Expert Practitioners: Their Validity and Significant Contribution to Translational Research. Sage Research Method Cases Part 2, 4-15.
- Ahmed, S. (2020). “A Literature Review on Scope Change Management in Construction Projects.” Journal of Engineering, Project, and Production Management.
- Al-Hajj, A., & Zraunig, M. (2018). The impact of project management implementation on the successful completion of projects in construction. International Journal of Innovation, Management and Technology, 9(1), 21-27.
- Blichfeldt, B. S. (2012). “Project Scheduling under Resource Constraints: A Chin, Chin, C. M. M., and Spowage, A. C, 2010. Defining and Classifying Project Management Methodologies. PM World Today, 12(5), 1-9.
- Chin, C. M. M., Spowage, A. C. 2012. Project Management Methodologies: A Comparative Analysis. Journal for the Advancement of Performance Information and Value, 4 (1), 106-118.
- Charvat, J., Project management methodologies: selecting, implementing and supporting methodologies and processes for projects. 2003: John Wiley & Sons. 2. Combined Constraint Programming and Mixed Integer Programming Approach.” International Journal of Production Economics.
- Doloi, H., Sawhney, A., Iyer, K.C., Rentala, S. (2012).: Analysing factors affecting delays in Indian construction projects. Int. J. Proj. Manag. 30, 479–489 https://doi.org/10.1016/j. ijproman.2011.10.004
- Faridi, A., El-Sayegh, S. (2006).: Significant factors causing delay in the UAE construction industry. Constr. Manag. Econ. 24, 1167–1176
- Heerkens, Garry. R. (2002). Project management.
- Jovanovic, P., & Beric, I. (2018). Analysis of the available project management methodologies. Management: Journal of Sustainable Business and Management Solutions in Emerging Economies, 23(3), 1-13.
- Karaman, E., & Kurt, M. (2015). Comparison of project management methodologies: prince 2 versus PMBOK for it projects. Int. Journal of Applied Sciences and Engineering Research, 4(4), 572-579.
- Kum, S., & Sahin, B. (2015). A root cause analysis for Arctic Marine accidents from 1993 to 2011. Safety science, 74, 206-220.
- Kerzner, H. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
- Leus, R. (2016). “The Impact of Resource Constraints on Project Scheduling Decisions.” European Journal of Operational Research.
- Lindhard, S., Wandahl, S. (2014): Scheduling of large, complex, and constrained construction projects – an exploration of LPS application. Int. J. Proj. Organ. Manag. 6, 237–253. https://doi.org/10.1504/IJPOM.2014.065258
- Marchesin, M. M., Monetti, E., & Da Rocha Lima Júnior, J. (2015). Analysis of Project Management Process Groups in urban renewal in the city of São Paulo. Journal of Urban Regeneration & Renewal, 8(4), 401-412.
- Mbala, M., Aigbavboa, C., & Aliu, J. (2019). Causes of delay in various construction projects: A literature review. In Advances in Human Factors, Sustainable Urban Planning and Infrastructure: Proceedings of the AHFE 2018 International Conference on Human Factors, Sustainable Urban Planning and Infrastructure, July 21-25, 2018, Loews Sapphire Falls Resort at Universal Studios, Orlando, Florida, USA 9 (pp. 489-495). Springer International Publishing.
- Milosevic, D. and P. Patanakul 2005, Standardized project management may increase development project success. International Journal of Project Management. 23: p. 181-192
- Sambasivan, M., Soon, Y.W (2007).: Causes and effects of delays in Malaysian construction industry. Int. J. Proj. Manag. 25, 517–526. https://doi.org/10.1016/j.ijproman.2006. 11.007
- Palaniappan, A. P. (2018). “Time, Cost and Quality Trade-offs in Project Management: A Case Study.” International Journal of Project Management.
- Project Management Institute. (2017). PMBOK Guide – 6th Edition. In the Project Management Institute.
- Singh, R., and Lano, K., 2014. Literature Survey of previous research work in Models and Methodologies in Project Management. International Journal of Advanced Computer Science and Applications, 5 (9), 107-122.
- Sterman, J. D. (2014). “Learning from Evidence in a Complex World.” American Journal of Public Health.
- Siegelaub, J.M., 2004. How PRINCE2® Can Complement the PMBOK® Guide and Your PMP, 2004 PMI Global Congress Proceedings.
- Smith, J., & Johnson, A. (2018). The impact of employee competence on project success. International Journal of Project Management, 36(4), 650-662
- Sweis, R. J., Bisharat, S. M., Bisharat, L., & Sweis, G. (2014). Factors affecting contractor performance on public construction projects. Life Science Journal, 11(4s), 28-39.
- Trading Economics, (2023, 12 April). Indonesia GDP from Construction. Indonesia GDP From Construction – 2023 Data – 2024 Forecast – 2010-2022 Historical (tradingeconomics.com)
- Thakkar, Jitesh J., 2022. Project Management: Strategic and Operation Planning, Management and Industrial Engineering, Spinger, 2022.
- Seers, Kate., 2012. Qualitative data analysis. Evidence Based Nursing. British Medical Journal (BMJ), 15(1), 2.